On November 13 local time, the main structure concreting of the cast-in-place culvert for the Aris broken bridge rehabilitation project in Namibia, undertaken by China Railway Seventh Group, was successfully completed. Over 100 days and nights since construction commenced, the project team installed a total of 180 tonnes of reinforcing steel and poured 1,965 cubic meters of concrete, completing key construction milestones ahead of schedule and laying a solid foundation for opening the bridge to traffic before the rainy season to benefit local livelihoods.